Date: Issue 63 - September 2015
Turmaks which provides defenceand civil / healthcare solutions, awarded a contract by Rwanda MoD for establishing Level II mobile field hospital with 30 beds and a staff camp for 70 staff be installed in UN camp Bria-CAR. The field hospital was manufactured in nine weeks after the contract and but it took approximately 10-12 weeks to deliver and 3 weeks to install the field hospital and camp in designated area due to the security challenges and circumstances.
Besides establishing and installing of field hospital and camp Turmaksprovided all medical and operational units such as generators, water treatment systems, incinerator and medical gas systems. The hospital is able to produce its own medical Oxygen as well.